Friday 21 March 2014

Having been away for just over a week, three main things have happened:  first, the North end gym exit doors have been removed, and a new temporary door is installed on the West side of the gym.  Second, the excavation 'hole' is particularly deep at the West end of the site - And to reinforce the gym wall and prepare to have the South wall of the new school secured, 'shoring' has taken place under the gym, extending out into what will be future under the new school.



Over the coming 2 weeks, March 24 - April 4, we will see:
  1. Completing of the shoring work
  2. Completion of the exit door and the framing work around it
  3. Completion of the removal of debris down the remaining 10 feet (to a max. of 18')
  4. Laying the foundation forms for the west end of the school.
The site also now has its own source of power with Hydro connecting the lines to the power pole last Friday - that means that there is heat and light inside the trailer on site - YEAH!