Thursday 26 February 2015

A view from the top... at the "top out" party!

Those in the know, ensured that our Parish hosted a TOP OUT PARTY today to celebrate the closing of the roof, and thank the trades that are working on our site.  At the gathering, held on the 3rd floor in the area facing south, were Father Andrzej, our Building Committee, leaders from our contractors, Yellowridge, our architect, other invited guests, our Owner's Representative and many people from the trades that are currently working on the site. Vic Vela organized a great Greek lunch for all, and accumulated prizes were shared with the workers as another sign of our thanks.

The photos represent views from the 3rd floor, both looking east, and south.  (The view from way up there is amazing - and I can hardly wait till everyone can walk inside what has been dreamed of, planned for and created by everyone's generosity.)

We keep the workers in our continual prayers - and thank all our donors for helping us get this far!










Monday 16 February 2015

Progress Photos



From the 7th Avenue corner into the Resource Room on the second floor

 Looking south on 7th Avenue into the entrance way and at the Multipurpose Room on second floor


Thursday 12 February 2015

A faithful reader of this BLOG nudged me today to pick up the story for our readers, which she's been keeping up with over the course of the past fifteen months... Apologies to all for the month of quiet; we assure you that the only part of school-life that is quiet is the BLOG!  Life in School and outside on our side continues to be vibrant, ever-changing and filled with newness.

Our staff has been working hard to expand opportunities for PHYSICAL ACTIVITY, and you can read our FRONT PAGE website stories to get a flavour for insights into some of the adventures that we've been able to provide for our students.  There have been skating, curling, bowling, and walking stories in abundance - and with four and a half months left in the school year, there will be many more to come.

On our building site, January was consumed with a visible transition with the removal of the forming materials and containers,  finishing of the roof pouring this past week, and the beginning of the framing for soon-to-be-installed windows.  Insulation has begun to arrive in huge bundles and some has been installed on the south facing walls.

Now we can actually see through the window frames from the south to the northern most classrooms, and the resource area on the east wall of the school is now boldly open and causing much excitement as we all are envisioning what is to come.

We will include some photos from January over the weekend, and then this coming week, I'll get some photos of 'up close' shots.

The School is hosting its annual ANNUAL GENERAL MEETING, Monday the 16 of February for all new and returning parents.  There will be a presentation by our building committee included in the meeting. 

We will be reaching our ONE YEAR mark this coming week - thanks to everyone who is working hard to see this big task completed.