so much to see... Tuesday, October 21, much more concrete was poured on the upper deck.  We all think that it was a bit of a miracle that the big rains in the forecast held off till the pour was completed.
Nonetheless, into the night and during the day on Wednesday, big machines helped to level off the concrete in preparation for future smooth flooring installation.





Once inside the building, the split level design of the school becomes abundantly apparent as the 'visitor' chooses to go up  l/2 floor or down l/2 floor. The five classroom spaces on each level are becoming more obvious, and huge spaces await the installation of future windows. 

(If you take a minute to go back into blog photos over the past six weeks, you can readily see the progress that has occured recently.)

The children continue to pray for the safety of all those workers spending their days to build us a 'school all bright and new'.